Overview of the project

General Phasing of works

Traffic management

Present – 30th of October 2026

Area 1

  • Kerbing and footpaths works on the south side of the road from Roslevan roundabout to Sean Dun
  • Installation of services and drainage on the south of Roslevan roundabout
  • Taring and finishing works on Roslevan roundabout to Sean Dun

Area 2

  • Kerbing and footpath works on the North side of the road each side of Cappahard roundabout
  • Installation of services and drainage
  • Taring and finishing works on the North side of the road each side of Cappahard roundabout